Project: project schedule

Build the schedule of a real website project: count working days without weekends and holidays, plan the testing phase, date the invoices and report the working days left on a status date.

Exercise 1 of 6

Count the working days of each task

This is the schedule of a website redesign. In D2:D7, count the working days of each task, from its start date (column B) to its end date (column C), with NETWORKDAYS.

TaskStartEndWorkdays
Kick-off & brief02/03/202606/03/2026
Design09/03/202627/03/2026
Content writing16/03/202610/04/2026
Development30/03/202608/05/2026
Integration11/05/202626/05/2026
Training27/05/202605/06/2026